An Approachable Guide to Financial Statements for Contractors

Published
Jul 23, 2026
Share

Key Takeaways

  • Your financial statements are not just a reporting requirement; they directly determine your bonding capacity, borrowing costs, and ability to win work.
  • The work-in-progress (WIP) schedule and a strong working capital position are the two things surety companies and lenders scrutinize most closely, and inaccurate cost-to-complete estimates are the most common problem with contractor financial statements.
  • A monthly close cadence with joint project manager and finance reviews catches estimate drift early before it erodes the financial statement reader’s confidence.
  • Audited or reviewed financial statements are an important tool for contractors to obtain higher bonding limits, lower borrowing costs, and faster bid approvals.

If you are a contractor or construction firm owner, your financial statements do more than satisfy an accounting requirement. They are the documents your surety and your lender use to decide how much they trust you. Also, your management team should use this information to compile strong bidding documentation to secure new projects with existing and new customers.

In short, strong financial statements open doors: higher bonding capacity, better loan terms, and credibility that wins bids. Weak or unclear financials close them.

This guide breaks down the key components of contractor financial statements, explains what surety companies and lenders are looking for, and walks through the practices that keep your numbers clean and your capacity growing.

Three Statements That Matter

Contractor financial statements have three core components:

  1. The balance sheet is a snapshot of your financial strength. Of everything on it, working capital, the cushion between current assets and current liabilities, is the measure that sureties and lenders weigh most heavily, since it shows whether you have the liquidity to sustain operations and take on new projects.
  2. The income statement shows the results of operations for the period, highlights margin trends, and the level of overhead incurred by the company.
  3. The work-in-progress (WIP) schedule is where the story of your job lives. It shows contract values, costs incurred, estimated costs to complete, revenue recognized, and billings to date for every active project. It tells a reader whether you are underbilling or overbilling, whether your margins are holding, and whether your estimates are reliable. If your WIP schedule is messy, nothing else in the financial package will fully compensate for it.

What Surety Companies and Lenders Are Really Looking For

When a surety or lender reviews your financial package, they are building a picture of risk. The numbers they focus on include:

  • Working capital and liquidity. Can you fund job costs while waiting on receivables and retainage? For many sureties, this is the first number they check, often before they even open the WIP schedule.
  • A clean WIP Schedule with minimal under-billings. Under-billings are a red flag. They can signal that costs are running ahead of billings, which may indicate losses the contractor has not yet recognized. Overbillings are generally a healthy situation, but it could pose liquidity challenges in the near term when the flow of new work diminishes.
  • Consistent margins and low profit fade. If your estimated margins keep shrinking as jobs progress, that pattern tells a reader your initial estimates may not be reliable.
  • Healthy backlog and pipeline. A strong backlog shows future revenue; the reader wants to see that it is diversified and not concentrated on one or two large projects.
  • Timely closes and clean reporting. If your financial statements are late or inconsistent, it raises questions about your internal controls and management discipline.

The Most Common Pitfall: Stale Cost-to-Complete Estimates

Of all the issues contractors run into with their financials, the most common is failing to keep cost-to-complete estimates current. The cost-to-complete is the foundation of the entire WIP schedule. When it is stale, everything downstream is wrong: Your percent complete is wrong, your recognized revenue is wrong, and your margin picture is wrong.

This is where profit fade comes from. A job starts with a projected 10% gross margin. Six months in, the estimate has not been updated, but costs have crept up. By the time the project closes, the actual margin is 4%. That pattern, repeated across several jobs, tells a financial statement reader that your estimating and bidding processes have a problem. It erodes confidence.

The fix is not complicated, but it requires discipline: Update cost-to-complete estimates monthly, tie them to actual job costing, and make sure your project managers and finance team review them together. When the PM, who is on the job every day, and the accountant, who sees the numbers, are in the same room, estimate drift gets caught early.

Other Pitfalls to Watch For

Beyond stale estimates, contractors commonly stumble in a few other areas:

  • Front-loading billings. Billing ahead of progress can look like cash strength on the surface, but without proper reconciliation, it masks the true financial position.
  • Poor change order capture. Approved and pending change orders that are not reflected in the WIP distort the job’s financial picture.
  • WIP disconnected from job costing. If your WIP schedule is maintained separately from your job cost system, the two will inevitably diverge. They need to be tied together.

Why Audited or Reviewed Financials Are Worth It

Some contractors view audited or reviewed financial statements as an expense they would rather avoid. The reality is that they are an investment. Audited financials with clean WIP reporting and strong working capital directly increase your bonding capacity. The process of going through an audit instills proper internal accounting and financial management discipline. They give lenders confidence in your ability to manage the company and thus the projects they are underwriting. Confidence in your financial reporting, as much as your technical ability to complete projects, is a key factor in their underwriting process. Strong relationships with sureties and lenders can be the difference maker when you are trying to win projects and perform work.

The contractors who treat their financial statements as a strategic tool, not just a compliance exercise, are the ones who grow their capacity year over year.

Getting Started

If you are looking to strengthen your financial reporting, start with these steps:

  1. Establish a monthly close cadence with joint PM and finance reviews.
  2. Tighten your cost-to-complete and change order capture procedures. This generally involves project managers, company leadership’s direct involvement and not just an accounting function. The tone at the top and built in accountability will make the difference between successful companies and those that are not successful.
  3. Standardize your WIP and backlog reporting with consistent templates and controls.
  4. Run a quarterly scorecard covering working capital, leverage, cash flow, backlog ratio, and DSO.
  5. Review your financial statements before submitting them to your surety or lender.

Remember: clear, accurate financial statements are the foundation of bonding capacity and lender confidence. If you have questions about your construction accounting, financial reporting, or audit readiness, EisnerAmper’s Construction team can help.

This article was prepared with AI assistance and edited and enhanced by EisnerAmper professionals for accuracy and completeness. All technical content, analysis, and recommendations reflect the knowledge of our team.

What's on Your Mind?

a man in a suit

Michael Stuhltrager

Michael Stuhltrager is a Senior Manager at the firm's Attest Real Estate Services Group and has 20 years of experience. 


Start a conversation with Michael

Receive the latest business insights, analysis, and perspectives from EisnerAmper professionals.